Nuclear Power Plant Lingen/Ems, boiling water reactor with fossil superheater with an electric gross output of 240 MW (82 MW of which from the fossil superheater). Nuclear commissioning on 31st January 1968; final shutdown on 5th January 1977; cumulative power generation: 11 TWh. Decommissioning was approved on 21st November 1985. Since the 30th March 1988 the plant is in the "safestore" condition which, according to the approval, continues for 25 years.